Construction begins on the Eggishorn project

  • Media release
  • 30/06/2026

Planning approval for the Eggishorn project has not yet been granted. To move forward with construction, Aletsch Bahnen applied for partial approval, which was granted on 9 June 2026.

The partial approval allows preparatory work to begin as early as 2026, ensuring that the main construction work can start immediately after the winter season in spring 2027.

The material cableways now being installed will enable the main construction work to begin immediately after the winter season in spring 2027, regardless of weather conditions.

The new cable car to the Eggishorn, including the restaurant, is scheduled to open at the start of the 2028 winter season.